Downtown Project
Reconstructing Downtown's Streets and Infrastructure
The Downtown Simpsonville Project is a multi-year effort to reconstruct downtown streets and the infrastructure beneath them while improving sidewalks, drainage, utilities, lighting, landscaping, traffic signals, and other elements of the public realm.
Construction began in August 2026 and will occur in phases across approximately 2 miles of Downtown streets.
Project Schedule
Construction is expected to take at least 24 months. The schedule may change based on construction conditions, utility coordination, weather, and the final scope of work.
Project information is current as of September 2026.
Get Downtown Project Updates
Text DowntownSVL to 38276 for construction updates, traffic changes, and other project information.
01 — Completed Projects
City Park and Municipal Campus
City Park and the municipal campus have been completed and are open to the public.
These projects were constructed as individual sites. The streets connecting them to the surrounding downtown area remained largely in their previous condition.
The Downtown Simpsonville Project addresses those connecting streets and the infrastructure beneath them.
02 — Project Scope
The Downtown Simpsonville Project encompasses approximately 2 miles of downtown streets across ten street segments:
- NE Main Street
- SE Main Street
- W. Curtis Street
- E. Curtis Street
- W. College Street
- E. College Street
- Academy Street
- Jonesville Road
- N. Main Street, from W. Curtis Street to W. College Street
- Hedge Street, from E. Curtis Street to E. College Street
The work includes reconstruction and improvement of infrastructure beneath and around the streets, including:
- Drainage system replacement and improvements and utility relocation and undergrounding
- Roadbed reconstruction and new pavement
- Sidewalks, curbs, accessible ramps, and landscaping
- Street lighting and traffic signal improvements
03 — Construction Phasing
Construction will occur in phases rather than closing the entire project area at once.
Individual street segments will be reconstructed in sequence. The City and contractor will coordinate construction activities to maintain access to downtown businesses, residences, public facilities, and emergency services throughout the project.
Current Construction Phase
Phase 1, College Street & Poinsettia Drive:
Project Schedule
The construction schedule will be updated as work progresses. Individual phases may change based on field conditions, utility work, weather, contractor operations, and other factors.
04 — Downtown Traffic Pattern
One of the most significant changes associated with the project is the future traffic pattern in the downtown core.
One-Way Circulation
When construction is complete, portions of downtown will operate as a one-way, two-lane circulation system.
- Curtis Street will operate eastbound from Maple Street through downtown to College Street.
- College Street will operate westbound from Curtis Street to Maple Street.
- Academy Street will operate northbound from Curtis Street to College Street.
Together, these streets form a counter-clockwise circulation loop around the downtown core.
The City has published this general traffic pattern since 2022. The map above reflects the configuration planned as part of the current project.
Streets Outside the One-Way Loop
The one-way circulation applies to the downtown core only.
E. Curtis Street east of College Street will remain two-way, with a new center turn lane.
Main Street and Curtis Street include state-maintained routes. The South Carolina Department of Transportation (SCDOT) has jurisdiction over certain aspects of those routes, including lane assignments and traffic signals. The City is coordinating with SCDOT as the project is designed and constructed.
Why a One-Way System?
The downtown traffic pattern was developed as part of the overall street and transportation design.
A one-way system can simplify vehicle movements through the downtown core by reducing conflicting vehicle movements at intersections. It also creates opportunities for shorter pedestrian crossings and allows two lanes of traffic traveling in the same direction.
The circulation loop provides a predictable route through the downtown core while accommodating access to downtown destinations.
The project traffic analysis was reviewed by SCDOT.
What Will Change for Drivers?
Not every trip through downtown will follow the same path after construction.
For some destinations, drivers may need to continue around the circulation loop rather than turn around or travel against the direction of traffic. Depending on the origin and destination, this may add approximately one or two blocks of travel.
The City will install signs and pavement markings to identify the new traffic pattern.
Traffic operations will be monitored after implementation, and adjustments will be made when warranted.
05 — Design Documents and Concepts
The City has developed design plans and concepts for several areas of downtown. These materials do not all represent the same stage of the project.
Included in the Current Construction Project
The following improvements are included in the current construction contract:
07 — Why Did Construction Begin in 2026
The Downtown Simpsonville Project was approved in 2021, but construction did not begin until August 2026.
The intervening period included engineering design, funding coordination, permitting, utility coordination, and coordination with SCDOT and other agencies.
The project required design of drainage, utilities, streets, sidewalks, traffic signals, and related infrastructure across multiple downtown street segments. The City also coordinated with the railroad and utility providers whose infrastructure is located within the project area.