Downtown Project

Reconstructing Downtown's Streets and Infrastructure

The Downtown Simpsonville Project is a multi-year effort to reconstruct downtown streets and the infrastructure beneath them while improving sidewalks, drainage, utilities, lighting, landscaping, traffic signals, and other elements of the public realm.

Construction began in August 2026 and will occur in phases across approximately 2 miles of Downtown streets.

Project Schedule

Construction is expected to take at least 24 months. The schedule may change based on construction conditions, utility coordination, weather, and the final scope of work.

Project information is current as of September 2026.

Get Downtown Project Updates

Text DowntownSVL to 38276 for construction updates, traffic changes, and other project information.

01 — Completed Projects

City Park and Municipal Campus

City Park and the municipal campus have been completed and are open to the public.

These projects were constructed as individual sites. The streets connecting them to the surrounding downtown area remained largely in their previous condition.

The Downtown Simpsonville Project addresses those connecting streets and the infrastructure beneath them.

02 — Project Scope

The Downtown Simpsonville Project encompasses approximately 2 miles of downtown streets across ten street segments:

  • NE Main Street
  • SE Main Street
  • W. Curtis Street
  • E. Curtis Street
  • W. College Street
  • E. College Street
  • Academy Street
  • Jonesville Road
  • N. Main Street, from W. Curtis Street to W. College Street
  • Hedge Street, from E. Curtis Street to E. College Street

The work includes reconstruction and improvement of infrastructure beneath and around the streets, including:

  • Drainage system replacement and improvements and utility relocation and undergrounding
  • Roadbed reconstruction and new pavement
  • Sidewalks, curbs, accessible ramps, and landscaping
  • Street lighting and traffic signal improvements
THIS IMAGE NEEDS TO BE REPLACED

03 — Construction Phasing

Construction will occur in phases rather than closing the entire project area at once.

Individual street segments will be reconstructed in sequence. The City and contractor will coordinate construction activities to maintain access to downtown businesses, residences, public facilities, and emergency services throughout the project.

Current Construction Phase

Phase 1, College Street & Poinsettia Drive:

THIS IMAGE NEEDS TO BE REPLACED

Project Schedule

The construction schedule will be updated as work progresses. Individual phases may change based on field conditions, utility work, weather, contractor operations, and other factors.

THIS IMAGE NEEDS TO BE REPLACED

04 — Downtown Traffic Pattern

One of the most significant changes associated with the project is the future traffic pattern in the downtown core.

One-Way Circulation

When construction is complete, portions of downtown will operate as a one-way, two-lane circulation system.

  • Curtis Street will operate eastbound from Maple Street through downtown to College Street.
  • College Street will operate westbound from Curtis Street to Maple Street.
  • Academy Street will operate northbound from Curtis Street to College Street.

Together, these streets form a counter-clockwise circulation loop around the downtown core.

The City has published this general traffic pattern since 2022. The map above reflects the configuration planned as part of the current project.

Streets Outside the One-Way Loop

The one-way circulation applies to the downtown core only.

E. Curtis Street east of College Street will remain two-way, with a new center turn lane.

Main Street and Curtis Street include state-maintained routes. The South Carolina Department of Transportation (SCDOT) has jurisdiction over certain aspects of those routes, including lane assignments and traffic signals. The City is coordinating with SCDOT as the project is designed and constructed.

Why a One-Way System?

The downtown traffic pattern was developed as part of the overall street and transportation design.

A one-way system can simplify vehicle movements through the downtown core by reducing conflicting vehicle movements at intersections. It also creates opportunities for shorter pedestrian crossings and allows two lanes of traffic traveling in the same direction.

The circulation loop provides a predictable route through the downtown core while accommodating access to downtown destinations.

The project traffic analysis was reviewed by SCDOT.

What Will Change for Drivers?

Not every trip through downtown will follow the same path after construction.

For some destinations, drivers may need to continue around the circulation loop rather than turn around or travel against the direction of traffic. Depending on the origin and destination, this may add approximately one or two blocks of travel.

The City will install signs and pavement markings to identify the new traffic pattern.

Traffic operations will be monitored after implementation, and adjustments will be made when warranted.

05 — Design Documents and Concepts

The City has developed design plans and concepts for several areas of downtown. These materials do not all represent the same stage of the project.

Included in the Current Construction Project

The following improvements are included in the current construction contract:

07 — Why Did Construction Begin in 2026

The Downtown Simpsonville Project was approved in 2021, but construction did not begin until August 2026.

The intervening period included engineering design, funding coordination, permitting, utility coordination, and coordination with SCDOT and other agencies.

The project required design of drainage, utilities, streets, sidewalks, traffic signals, and related infrastructure across multiple downtown street segments. The City also coordinated with the railroad and utility providers whose infrastructure is located within the project area.

Monthly Check Register

General Fund Un-audited Account Payments

Sewer Fund Un-audited Account Payments

Submit a question or episode idea for the SIMPLY SAID. Podcast:

SIMPLY SAID. Podcast Questions Form
Rate the show:

Monthly Financial Update

September 2026 Overview
August 2026- Financial Report
July 2026- Financial Report
June 2026- Financial Report
May 2026-Financial Report
April 2026-Financial Report
March 2026-Financial Report
February 2026-Financial Report
January 2026-Financial Report
December 2025-Financial Report
November 2025-Financial Report
October 2025-Financial Report
September 2025-Financial Report
August 2025
July 2025
June 2025
May 2025
April 2025
March 2025
February 2025
January 2025
December 2024
November 2024
October 2024
September 2024
August 2024
July 2024
June 2024
May 2024
April 2024
March 2024
February 2024
January 2024
December 2023
November 2023
October 2023
September 2023
August 2023
July 2023
June 2023
May 2023
April 2023
March 2023
February 2023
January 2023
December 2022
November 2022
October 2022
September 2022
August 2022
July 2022
June 2022
May 2022
April 2022

Comprehensive Annual Financial Reports (Audit Reports)

FY 2024-2025
FY 2023-2024
FY 2022-2023
FY 2021-2022
FY 2020-2021
FY 2019-2020
FY 2018-2019
FY 2017-2018
FY 2016-2017
FY 2015-2016
FY 2014-2015
FY 2013-2014
FY 2012-2013
FY 2011-2012
FY 2010-2011
FY 2009-2010
FY 2008-2009
FY 2007-2008
FY 2006-2007
FY 2005-2006
FY 2004-2005

Your Email Subscriptions

Email Subscriptions
Select the newsletter(s) to which you want to subscribe or unsubscribe.